Merseyrail Hunts Cross to Liverpool Central Closure: 11 October to 6 November 2026

Merseyrail Hunts Cross line closes 11 Oct to 6 Nov 2026. Check replacement buses to Moorfields or Sandhills, Sunday Wirral changes and 7 Nov reopening.

By Brian K · 17 Sep 2026 · Updated 9 Oct 2026 · 9 min read

In this storyClosure dates and replacement bus arrangements
  1. Closure dates and replacement bus arrangements
  2. Two Anfield match days fall on closure Sundays
  3. Which Merseyrail stations lose their normal service?
  4. What happens Monday to Saturday?
  5. Sundays are different
  6. Why does the railway need to close for 26 days?
  7. This railway has been running beneath Liverpool for generations
  8. Similar tunnel work was carried out in 2022
  9. The railway's electrical controls are being upgraded too
  10. Liverpool Central itself is not closing
  11. Travelling from Hunts Cross
  12. Travelling from Liverpool South Parkway
  13. Travelling from Cressington and Aigburth
  14. Travelling from St Michaels
  15. Travelling from Brunswick
  16. Changing for Southport, Ormskirk or Headbolt Lane
  17. Sandhills becomes much more important on Sundays
  18. Liverpool Baltic is being built on the affected railway
  19. The closure covers half-term and Halloween
  20. Check where your replacement bus actually stops
  21. Accessibility and assisted travel
  22. How much extra time should you allow?
  23. Five things to check before 11 October
  24. When do normal trains return?
  25. Useful links and sources

Quick answer: Hunts Cross line closure at a glance

  • Closed section: Northern Line between Hunts Cross and Liverpool Central (Brunswick, St Michaels, Aigburth, Cressington, Liverpool South Parkway, Hunts Cross).
  • Closure dates: Sunday 11 October to Friday 6 November 2026 (26 days). Normal services resume Saturday 7 November.
  • Monday to Saturday: Replacement buses run between Hunts Cross and Moorfields (calling at intermediate stations; buses do not call at Liverpool Central). Northern Line trains from the north continue to Liverpool Central.
  • Sundays (11, 18, 25 Oct & 1 Nov): Replacement buses run between Hunts Cross and Sandhills. Trains from Southport, Ormskirk and Headbolt Lane terminate at Sandhills. Wirral Line trains terminate at James Street on 11 and 18 October.
  • Liverpool Central: Central is not completely closed. Trains from Southport, Ormskirk and Headbolt Lane still serve Central Monday–Saturday.

Sunday 11 October Event Travel Alert: Major weekend events coincide with the first closure Sunday. If travelling to Comic Con Liverpool at ACC Liverpool or the Liverpool v Manchester City match at Anfield (4.30pm kick-off), allow extra time. From Hunts Cross take the replacement bus to Sandhills; from the north trains stop at Sandhills (connect with the Soccerbus to Anfield). See our weekend guide for full travel options.

Merseyrail's Northern Line between Hunts Cross and Liverpool Central will close from Sunday 11 October to Friday 6 November 2026.

Network Rail is spending £3.5 million strengthening and waterproofing four tunnels on the southern approach to Liverpool city centre. The work is intended to stop water getting into the tunnels and affecting the railway's electrified third rail.

For passengers the important bit is simpler: there will be no Northern Line trains between Hunts Cross and Liverpool Central during the closure. Replacement buses will run, but the arrangements change on Sundays, and Liverpool Central itself is not completely closed.

Normal Northern Line services are currently due to resume on Saturday 7 November 2026.

Travelling on Sunday 11 October? Trains from Southport, Ormskirk and Headbolt Lane will finish at Sandhills, not Liverpool Central. Replacement buses from Hunts Cross also run to Sandhills on Sundays, rather than Moorfields. Wirral Line trains will finish at James Street. It is also Liverpool v Manchester City at Anfield, with a 4.30pm kick-off. Check your route before setting off.

Closure dates and replacement bus arrangements

WhenWhat changes
11 October to 6 NovemberNo Northern Line trains between Hunts Cross and Liverpool Central.
Monday to SaturdayReplacement buses between Hunts Cross and Moorfields. Northern Line trains from the north continue to Liverpool Central.
Sundays 11, 18 and 25 October, and 1 NovemberReplacement buses between Hunts Cross and Sandhills. Trains from Southport, Ormskirk and Headbolt Lane terminate at Sandhills.
Sundays 11 and 18 OctoberWirral Line trains terminate at James Street. No Wirral Line trains serve Moorfields, Lime Street or Liverpool Central.
Sundays 25 October and 1 NovemberFurther Wirral Line closures and replacement buses. Check the Sunday-specific information below before travelling.
Saturday 7 NovemberNormal services are scheduled to resume.

Step-free travel warning for 11 and 18 October: James Street Platform 2 has no lift access, and New Brighton and Ellesmere Port services will call there. Merseyrail advises passengers needing step-free access to change at Hamilton Square for a Chester or West Kirby service. An accessible bus between Hamilton Square and Moorfields is planned every 30 minutes for Northern Line connections. Read the full accessibility arrangements in the Sunday section below.

The closure allows Network Rail to strengthen and waterproof four tunnels and upgrade electrical power controls at a cost of £3.5 million. These are planned arrangements, not live running information. Check Merseyrail's latest service information and your specific journey before travelling.

Two Anfield match days fall on closure Sundays

Liverpool play Manchester City at Anfield on Sunday 11 October (4.30pm BST) and Arsenal on Sunday 1 November (4.30pm GMT), according to Liverpool FC's fixture update. Both are days when Northern Line trains stop at Sandhills and no Northern Line trains reach the city-centre stations.

Merseyrail's match-day advice is to travel to Sandhills and connect with the Soccerbus. If you are coming from Hunts Cross or the stations in between, take the replacement bus to Sandhills, or use local city-centre buses to Anfield. Wirral Line supporters on 11 October should get off at James Street and walk or use local buses for city-centre connections.

Merseyrail's published match-day notes name 11 and 18 October for the Northern Line. The 1 November arrangements follow the same Sandhills pattern, but check Merseyrail's page in the days before the Arsenal game.

Network Rail issued a final reminder on 5 October 2026, and has published a full explanation of the Northern Line tunnel work. Merseyrail has a dedicated tunnel upgrade service information page covering the passenger arrangements.

Which Merseyrail stations lose their normal service?

The affected section runs through six stations before the railway reaches the city centre:

  • Hunts Cross
  • Liverpool South Parkway
  • Cressington
  • Aigburth
  • St Michaels
  • Brunswick

There will be no normal Northern Line train service through those stations into Liverpool Central during the work.

The effect will be particularly noticeable across South Liverpool, because this section provides the direct city-centre rail connection for areas including Hunts Cross, Garston, Cressington, Aigburth and the streets around St Michaels.

Liverpool South Parkway is also an interchange for other rail services, buses and journeys towards Liverpool John Lennon Airport. The closure does not mean every railway service at Liverpool South Parkway is suspended. It specifically affects Merseyrail's Northern Line.

What happens Monday to Saturday?

From Monday to Saturday, replacement buses will run between Hunts Cross and Moorfields.

Northern Line trains will continue operating between:

  • Liverpool Central and Southport
  • Liverpool Central and Ormskirk
  • Liverpool Central and Headbolt Lane

This means Liverpool Central remains open. If you normally travel into Liverpool Central from Southport, Waterloo, Crosby, Ormskirk, Aintree, Kirkdale or the Headbolt Lane branch, trains are still scheduled to reach Central from the north. It is the railway south of Liverpool Central towards Hunts Cross that closes.

There is one important difference for South Liverpool passengers: replacement buses will run to Moorfields rather than Liverpool Central.

Merseyrail says replacement buses cannot access certain roads in Liverpool city centre, so its rail replacement services use Moorfields or James Street depending on the line affected. Someone who normally steps off a train at Central may instead have an extra walk or an interchange from Moorfields.

Check the Merseyrail Journey Planner for the journey you actually intend to make.

Sundays are different

The four Sundays during the project have wider disruption.

On 11 October, 18 October, 25 October and 1 November, Northern Line trains from Southport, Ormskirk and Headbolt Lane will terminate at Sandhills rather than continuing through the city centre. Replacement buses will run between Hunts Cross and Sandhills.

The Wirral Line will also be affected.

A Merseyrail class 777 train at an underground platform at Liverpool James Street on a New Brighton service
James Street becomes the city-centre terminus for Wirral Line trains on the first two affected Sundays. Photo: Geof Sheppard (CC BY-SA 4.0) via Wikimedia Commons.

Sunday 11 and 18 October

Wirral Line trains from West Kirby, New Brighton, Chester and Ellesmere Port are scheduled to terminate at James Street. They will not serve:

  • Moorfields
  • Liverpool Lime Street
  • Liverpool Central

Both sides of Merseyrail's city-centre underground network are affected on those two dates.

No lift access at James Street Platform 2. Merseyrail says New Brighton and Ellesmere Port services will use Platform 2 at James Street on Sunday 11 and 18 October. There is no lift access to Platform 2.

Passengers who need step-free access are advised to travel to Hamilton Square and change there for a Chester or West Kirby service. Merseyrail says an accessible bus will also run between Hamilton Square and Moorfields every 30 minutes for passengers who need to connect with the Northern Line. Allow extra time if this affects your journey.

Sunday 25 October and 1 November

Wirral Line services will operate between:

  • West Kirby / New Brighton and Birkenhead North
  • Chester / Ellesmere Port and Rock Ferry

Replacement buses will operate between:

  • Birkenhead North and Moorfields
  • Rock Ferry and Moorfields

Northern Line services from the north will again terminate at Sandhills, with replacement buses between Hunts Cross and Sandhills. These are likely to be among the more complicated days to travel across the Merseyrail network during the project.

The official notices do not quite agree on these two Sundays. Merseyrail and Network Rail say the Wirral replacement buses run to Moorfields. National Rail's engineering notice lists them running from Birkenhead North and Rock Ferry to Hamilton Square instead. Check which applies on the morning you travel.

National Rail also says Chester station is closed until 08:05 on Sunday 1 November, with the first train replaced by a bus to Moorfields.

Check the National Rail engineering notice and the Merseyrail Journey Planner shortly before travelling on these Sundays.

Why does the railway need to close for 26 days?

The railway south of Liverpool Central passes through tunnels as it approaches the underground station. Network Rail says water entering four of these tunnels needs to be addressed.

This matters because Merseyrail trains use a 750-volt DC third rail for electricity. Unlike an overhead electrification system, the conductor rail supplying the trains sits alongside the running rails. Water entering the railway can therefore create problems for the electrical infrastructure.

Merseyrail says water ingress can contribute to:

  • power failures
  • emergency speed restrictions
  • unplanned closures

The project will waterproof and strengthen the affected tunnels. Network Rail says the scale and complexity of the work requires the railway to be closed rather than attempting to carry it out around normal train services.

This railway has been running beneath Liverpool for generations

There is useful history behind the closure, because the railway south of Central was not built as one modern Merseyrail project.

The original Liverpool Central high-level station opened in 1874, serving the Cheshire Lines Committee railway. The modern Northern Line emerged much later, from the reorganisation and connection of previously separate railways beneath Liverpool.

The 1970s Link Tunnel connected the railway approaching Liverpool from the south with lines running north towards Southport, Ormskirk and what is now the Headbolt Lane branch. That project created the cross-city Northern Line familiar to passengers today.

For readers interested in how the system developed, the Wikipedia articles on Liverpool Central railway station, the Northern Line and the wider history of Merseyrail provide useful background.

For the 2026 closure itself, though, go to Network Rail, Merseyrail and National Rail rather than Wikipedia, because the engineering and service arrangements can change.

Brunswick sits between two tunnel sections

Brunswick is an interesting point on this stretch of railway. The present station opened in 1998, although an earlier station carrying the Brunswick name had opened in 1864 and closed in 1874.

The modern station sits on a short open section of railway between tunnels, before trains continue towards Liverpool Central. There is more background on the history of Brunswick railway station.

That geography helps explain why passengers travelling a relatively short distance into Liverpool Central are affected by work taking place underground.

Similar tunnel work was carried out in 2022

This is not the first waterproofing project on the southern approach to Liverpool Central. Network Rail says similar improvements were made to High Neck Tunnel in 2022. The current project covers another four tunnels.

The aim is preventative. Network Rail says carrying out the work during a planned closure reduces the risk of water-related faults producing emergency closures or restrictions later.

The railway's electrical controls are being upgraded too

Engineers are using the closure to make changes beyond the tunnel walls. New track feeder switches will be installed as part of the continuing modernisation of Merseyrail's power-control system.

These switches allow engineers to isolate smaller sections of electrified railway remotely. That matters when something goes wrong. If engineers can switch off a smaller section rather than a longer stretch of railway, maintenance and fault repairs can potentially take place without removing power from as much of the network.

It is largely invisible infrastructure, but it is one reason Network Rail is doing several jobs during the same 26-day closure.

Liverpool Central itself is not closing

This is probably the most important distinction for passengers. Liverpool Central is not shutting for 26 days.

Monday to Saturday, Northern Line trains from Southport, Ormskirk and Headbolt Lane are scheduled to continue serving Liverpool Central.

What passengers cannot do is travel south from Central towards Brunswick, St Michaels, Aigburth, Cressington, Liverpool South Parkway or Hunts Cross.

Sunday arrangements are different, with Northern Line trains from the north terminating at Sandhills.

Travelling from Hunts Cross

Hunts Cross loses its normal Merseyrail connection towards Liverpool city centre throughout the project.

Monday to Saturday, the official rail replacement service runs towards Moorfields. On Sundays it runs towards Sandhills.

Hunts Cross is also served by other rail services, so passengers making longer journeys should check their complete route rather than assuming every train from the station has been cancelled.

Travelling from Liverpool South Parkway

Liverpool South Parkway needs slightly more planning, because Merseyrail is only one part of the station. The closure affects its Merseyrail Northern Line service, and other operators also call there.

The best alternative could depend heavily on where you are travelling. A passenger heading towards the city centre may have different options from someone changing for a longer-distance service.

The station is also used for journeys towards Liverpool John Lennon Airport, with onward bus connections. If your airport journey normally includes Merseyrail between Liverpool city centre and South Parkway, allow extra time and check the complete journey before setting off.

Travelling from Cressington and Aigburth

Cressington and Aigburth passengers lose their rail service during the closure.

The official alternative is the replacement bus, but it is sensible to compare that with the normal Liverpool bus network for your particular destination. A replacement bus travels on the same roads as everybody else, so journey times can be affected by normal South Liverpool congestion.

The morning and evening peaks are therefore likely to need more planning than simply leaving home at the same time as usual. Our guide to getting around Liverpool without a car covers the bus and walking options across this part of the city.

Travelling from St Michaels

St Michaels serves parts of Aigburth and is commonly used for the Lark Lane and Sefton Park area. There will be no normal Northern Line service at the station.

If your final destination is elsewhere in the city centre rather than close to Moorfields, compare the replacement service with normal bus routes before travelling.

Travelling from Brunswick

Brunswick is the final station before the Northern Line heads through the southern approach towards underground Liverpool Central. There will be no normal Northern Line trains from Brunswick during the closure.

For some passengers making the relatively short journey into central Liverpool, ordinary buses, walking or cycling may be alternatives to the replacement bus. The sensible choice will depend on mobility, weather and exactly where in the city centre you are going.

Changing for Southport, Ormskirk or Headbolt Lane

Passengers who normally travel through Liverpool Central from South Liverpool and continue north will need to change their routine.

Monday to Saturday, replacement buses run towards Moorfields. Moorfields is on the Northern Line, allowing passengers to continue towards Southport, Ormskirk and Headbolt Lane. On Sundays the interchange moves to Sandhills.

The reverse applies for passengers travelling towards South Liverpool. Allow extra time for the road journey and the interchange.

Sandhills becomes much more important on Sundays

Platforms and track at Kirkdale railway station in north Liverpool on a clear day
Kirkdale, the next station north of Sandhills, where the Ormskirk and Headbolt Lane branches split from the Southport line. Photo: JThomas (CC BY-SA 2.0) via Wikimedia Commons.

Sandhills will temporarily become the city-side terminus for Northern Line trains on the four affected Sundays. That means the closure has implications beyond South Liverpool.

Sandhills is served by trains towards Southport, Ormskirk and Headbolt Lane, making it a key connection point during the Sunday closure. It is also an important station for major football traffic in North Liverpool.

Anyone travelling for a football match or a large event on one of the affected Sundays should check the specific transport arrangements for that day rather than relying on their normal journey.

Liverpool Baltic is being built on the affected railway

Nineteenth-century warehouse and merchant buildings on Duke Street, Liverpool
The Baltic edge of the city centre, where the new Liverpool Baltic station is planned on the former St James site. Photo: Rept0n1x (CC BY-SA 2.0) via Wikimedia Commons.

There is another useful piece of context on this section. The new Liverpool Baltic station is being developed between Liverpool Central and Brunswick on the Northern Line, on the site of the former St James station.

Liverpool City Region Combined Authority says the new station is planned to include step-free access, passenger toilets and a cycle hub.

It is a separate project from the October tunnel closure, so the two should not be confused. For readers following changes to this railway, though, it means the stretch between Central and Brunswick is currently the subject of several substantial infrastructure projects.

The closure covers half-term and Halloween

The closure starts on 11 October and runs through the second half of October, including the school half-term period and Halloween weekend. Saturday 31 October falls inside the closure, so there will still be no Merseyrail trains between Hunts Cross and Liverpool Central. Replacement buses are scheduled between Hunts Cross and Moorfields.

Anyone travelling into the city from South Liverpool for an event should check their route before leaving rather than relying on their normal train.

Check where your replacement bus actually stops

Do not assume a replacement bus will leave from exactly the same place as your normal station entrance. Merseyrail publishes information for individual stations and directs passengers to its Journey Planner for current arrangements.

Check this before the first journey you make during the closure, particularly if:

  • you have limited mobility
  • you are travelling with children
  • you have luggage
  • you need to make another train connection
  • you are unfamiliar with the station

Accessibility and assisted travel

Passengers who need step-free travel or assistance should plan the complete replacement journey, not just check whether their normal railway station is accessible.

Moving part of a journey from rail to road can change where passengers board, alight and interchange. Merseyrail provides accessibility and assisted-travel information through its journey-planning service. Anyone relying on a lift should also check its status on the day.

How much extra time should you allow?

There is no useful single answer. A passenger travelling from Brunswick into the city centre is making a very different journey from somebody travelling from Hunts Cross to Southport.

Replacement buses can also be held up by road traffic in a way trains normally are not. Extra disruption could occur during:

  • weekday morning and evening peaks
  • school travel periods
  • football matchdays
  • large city-centre events
  • roadworks
  • busy weekends

Rather than adding an arbitrary 15 or 30 minutes to every trip, check the actual journey you intend to make.

Five things to check before 11 October

  1. Check whether you actually use the closed section. Liverpool Central remains served from the north Monday to Saturday.
  2. Find your replacement bus stop. Do this before your first affected journey rather than when you arrive at the station.
  3. Compare the replacement bus with normal buses. For some journeys into Liverpool, the existing bus network may be more direct.
  4. Pay particular attention to Sundays. The railway arrangements are substantially different from the Monday-to-Saturday service.
  5. Check again immediately before travelling. The closure is planned months in advance, and timetables and replacement arrangements can still be amended.

Use the Merseyrail Journey Planner and National Rail engineering information before travelling.

When do normal trains return?

Network Rail and Merseyrail currently say the work will finish on Friday 6 November 2026. Normal Northern Line services are scheduled to resume on Saturday 7 November.

Passengers travelling towards the end of the project should still check the service before leaving.

Share this story
Next readNext story →

Aigburth, Liverpool: Rents, Schools, Transport and What to Know

A guide to living in Aigburth, south Liverpool. House prices, rents, schools, Merseyrail and bus routes, Lark Lane, Sefton Park, Otterspool and Sudley House.

7 min read·Read full story →

Further background

Common questions

Is Liverpool Central station closed during the Merseyrail tunnel work?

No. Monday to Saturday, Northern Line trains from Southport, Ormskirk and Headbolt Lane are scheduled to keep serving Liverpool Central. What closes is the railway south of Central towards Brunswick, St Michaels, Aigburth, Cressington, Liverpool South Parkway and Hunts Cross. On the four affected Sundays, trains from the north terminate at Sandhills instead.

Where do the Merseyrail replacement buses run to?

Monday to Saturday they run between Hunts Cross and Moorfields. On Sunday 11, 18 and 25 October and Sunday 1 November they run between Hunts Cross and Sandhills. Merseyrail says replacement buses cannot access certain city-centre roads, which is why they call at Moorfields rather than Liverpool Central.

When do normal Merseyrail trains return between Hunts Cross and Liverpool Central?

Network Rail and Merseyrail currently say the work finishes on Friday 6 November 2026, with normal Northern Line services scheduled to resume on Saturday 7 November. Check the service before travelling towards the end of the closure.

Are trains running from Aigburth or Liverpool South Parkway to Liverpool Central?

No. There will be no Merseyrail Northern Line trains between Aigburth or Liverpool South Parkway and Liverpool Central from 11 October to 6 November. Replacement buses will operate. Other train operators that call at Liverpool South Parkway should be checked separately.

Will Merseyrail run normally on Halloween?

No. Saturday 31 October falls inside the closure, so there will still be no Merseyrail trains between Hunts Cross and Liverpool Central. Replacement buses are scheduled between Hunts Cross and Moorfields.

How do I get to Anfield on a closure Sunday?

Liverpool play Manchester City on Sunday 11 October (4.30pm BST) and Arsenal on Sunday 1 November (4.30pm GMT), both closure Sundays. Merseyrail's matchday advice is to travel to Sandhills and connect with the Soccerbus. From Hunts Cross, take the replacement bus to Sandhills or use local city-centre buses to Anfield.

Is there step-free access at James Street on Sunday 11 and 18 October?

Not on Platform 2, which New Brighton and Ellesmere Port services will use and which has no lift access. Merseyrail advises step-free passengers to travel to Hamilton Square and change there for a Chester or West Kirby service. An accessible bus will run between Hamilton Square and Moorfields every 30 minutes.

Comments

Join the conversation with your L1Local Community account. Keep it civil and on topic.

Liverpool this week

New places, local news, things to do and our latest guides. Weekly.

Free.

100% local

Written in Liverpool, about Liverpool

Independent

Not owned by a group or a party

Reader led

Tip-offs and corrections welcome

Free to read

No paywall, no registration